West Marin Rates 2025
West Marin Rate Study 2025
The North Marin Water District (District) faces several challenges ahead in West Marin: aging infrastructure, two bridges carrying our water mains being replaced by others (Caltrans and the County), new developments in Point Reyes Station, and water supply resiliency. The District has developed a comprehensive long-term Capital Improvement Program (CIP) that not only addresses aging infrastructure but also water supply resiliency. In addition, we are analyzing ways to fund these projects and the necessary water rates needed to have a sustainable enterprise. Because of these known near and long-term CIP projects combined with increasing impacts of inflation, electricity costs and other costs that affect supplies, operations and construction, the District Board of Directors initiated and completed a rate study for the West Marin Service Area. The rate study considered all of these impacts to appropriately plan for a long-term rate structure with a goal of establishing a secure, multi-year financial plan that supports operating costs and capital spending necessary to provide water services that are reliable, high-quality, environmentally responsible and reasonably priced, and ensure that the rate structure complies with the (evolving) requirements of Proposition 218 and was approved at the April 15, 2025 Board meeting. The April 15th meeting also included a presentation on the proposed rates which was a follow up to an earlier public workshop held on March 18th. Subsequently, a public hearing was held on June 17, 2025, and the new rates and rate structure were approved by the Board of Directors following the public hearing. This webpage contains various information on the rate development process and presents information on the rate increases and how it may affect your water bill as a residential or commercial customer in the West Marin Service Area. Click HERE for a link to the West Marin Water Rate Study.
The Rate Setting and Development Process

Rate Increase Drivers
Significant increase in capital spending
- In the near-term, costs are driven by two bridge projects (required by CalTrans/County) and Gallagher Well No.3 (needed for water supply)
- Also notable is a major water treatment plant (WTP) rehabilitation planned in 5 years
- The majority of the system is reaching the end of design life. For instance, NMWD uses useful life values for various assets:
- Water mains – 50 years
- Pumping equipment – 25 years
- Pump Stations – 50 years
- Water Treatment equipment – 20 years
- Buildings and Structures – 40 years
- Projects range from water main replacements to storage tank replacements over the next twenty years. Enhancing water supply resiliency and a complete rehabilitation of the Pt. Reyes Treatment Plant is also planned.
- Total projected costs for all planned capital improvement projects is currently estimated at 27.5 million.
Inflation
- Operating cost in FY2025 were budgeted at $922,000 vs. $664,000 forecasted by 2021 Financial Plan (an increase of $258,000, or 39%)
- Primarily from treatment, electric, and labor costs.
Fixed (Service Charge) vs. Variable (Water Use) Revenue
Approximately 11.2% of operating costs are variable
Approximately 5.7% of all costs are variable
However,
73.2% of rate revenue is currently variable, from the sale of water, which is not well balanced compared to fixed expenses.
We incrementally increased the proportion of revenue that is fixed, the bi-monthly service charge (by about 3%).

Proposed Rates and Water Bill Impacts
The rate study considered all of these impacts to appropriately plan for a long-term rate structure with a goal of establishing a secure, multi-year financial plan that supports operating costs and capital spending necessary to provide water services that are reliable, high-quality, environmentally responsible and reasonably priced, and ensure that the rate structure complies with the (evolving) requirements of Proposition 218. Through this process, the rate increases were recommended and approved in order to accomplish critical infrastructure upgrades, maintain reliable service, and ensure long-term financial stability.
More Information about the Rate Study and Hearing Process and the West Marin Service Area
- Prop 218 Mailer – West Marin – 2025
- Final West Marin Rate Study 2025
- Draft West Marin Rate Study March 2025
- West Marin Rate Study Board Presentation April 2025
- West Marin Rate Study Board Presentation March 2025
- Interview on KWMR with General Manager Tony Williams
- West Marin Water Service Area Factsheet
- West Marin Water Service Area Map
For questions, comments or inquiries regarding the West Marin Rate Study and rate development process, presentation events and rate hearings, please call 415-897-4133 or email info@nmwd.com.